EMBER GAS TECHNOLOGY SDN BHD (OFFSHORE)

CONTRACT HOLDER : REPSOL

Fitri

Tel.No.:013-3530406

TALISMAN BOA COL WATER SYSTEM UPGRADE

P.O.NO.: EGT/PO/TML/ABSB/001

278,000.00

Feb 2016

COMPLETED


PIPING / MECHANICAL


               2015
 

CLIENT ‘S NAMES

CLIENT’S CONTACT PERSON/TEL NO:

PROJECT NAME

CONTRACT VALUE

(RM)

PROJECT AWARDED

STATUS

PETRONAS GAS BERHAD

(SHAH ALAM REGIONAL OFFICE)

        1) En. Mohd Najib bin Ahmad

(mohd_najib@petronas.com.my)

        2) En. Muhammad Zahin Akmal bin Abd Ghani

(zahin.ghani@petronas.com.my)

Tel No: 03-55106222

PROVISION OF MANPOWER, EQUIPMENT, TOOLS, MATERIALS & CONSUMABLES TO PERFORM ABOVE GROUND STRUCTURE REHABILITATION (BLASTING, PAINTING & CIVIL WORK) AT SELECTED STATIONS AT SHAH ALAM REGIONAL OFFICE.

PO NUMBER: 412120120712

178,000.00

Sep 2015

COMPLETED


MATERIALS /PARTS (RETAILS SALES)


               2015 (At July)
 

CLIENT ‘S NAMES

 

CLIENT’S CONTACT PERSON/TEL NO:

PROJECT NAME

CONTRACT VALUE

(RM)

PROJECT AWARDED

STATUS

FMC WELLHEAD EQUIPMENT SDN BHD

        1) Yusmawati Yusup

 

Tel No: 07 2671000

 

SUPPLY OF SOCKET KEY OF TUBING.

PO NO: 4700010782

600.00

May 2015

COMPLETED

FMC WELLHEAD EQUIPMENT SDN BHD

        1) Noor Haiyati Mohd Jamal

Tel No: 07 2671000

SUPPLY OF PLYWOOD STAND

PO NO: 4700008938
 

5,000.00

May 2015

COMPLETED

FMC WELLHEAD EQUIPMENT SDN BHD

        1) Noor Haiyati Mohd Jamal

 

Tel No: 07 2671000

SUPPLY OF HYDRAULIC COUPLER PROTECTOR

SUPPLY OF SOCKET KEY OF TUBING.

PO NO: 4700008936
 

800.00

300.00

May 2015

COMPLETED

MALAYSIA MARINE AND HEAVY ENGINEERING SDN BHD

Contract Holder:-

PETRONAS CARIGALI SDN BHD

 

        1) Adilla Shuhada binti Mat Tap (adilla.shuhada@mmhe.com.my)

        2) Teo Muh Chow (mc.teo@mmhe.com.my)

 

Tel No: 07 2682111

 

SUPPLY OF PLATE GLAND

PO NO: 3700003675

1,250.00

Apr 2015

COMPLETED

BOUSTEAD PENANG SHIPYARD SDN BHD

 

 

1) Valery Briones (valery@bhic.com.my)

Tel No: 03 20316516

 

SUPPLY AND DELIVERY OF FURNITURE-BELUM TOPSIDE

PO NO: BPS/P-102592/4

 

8,900.00

 

Jan 2015

 

COMPLETED


MANPOWER SUPPLY


               2016
 

CLIENT ‘S NAMES

CLIENT’S CONTACT PERSON/TEL NO:

PROJECT NAME

CONTRACT VALUE

(RM)

PROJECT AWARDED

STATUS

MALAYSIA MARINE AND HEAVY ENGINEERING SDN.BHD.

 

Masuki bin Sidek

Tel No: 07-2682111

TO SUPPLY 6 COMPETENT RIGGERS (RAPID)

SO.NO.: 3900004379

42,552.00

Jan 2016

COMPLETED

MALAYSIA MARINE AND HEAVY ENGINEERING SDN.BHD.

 

Masuki bin Sidek

Tel No: 07-2682111

TO SUPPLY 5 COMPETENT RIGGERS (RAPID)

SO.NO.: 3900004661

106,380.00

April 2016

COMPLETED

MALAYSIA MARINE AND HEAVY ENGINEERING SDN.BHD.

Masuki bin Sidek

Tel No: 07-2682111

TO SUPPLY 4 COMPETENT RIGGERS (RAPID)

SO.NO.: 2300009614

28,368.00

May 2016

COMPLETED

MALAYSIA MARINE AND HEAVY ENGINEERING SDN.BHD.

 

Masuki bin Sidek

Tel No: 07-2682111

TO SUPPLY 8 COMPETENT RIGGERS AND 8 SEMI-SKILLED (RAPID)

SO.NO.: 3900005012

105,592.00

Jun 2016

COMPLETED

MALAYSIA MARINE AND HEAVY ENGINEERING SDN.BHD.

Nujaimi Abd Aziz

Tel No. : 07-2682111

Manpower supply for Riser Guard & Boatlanding (6 pax Helper, 3 pax helper)

SO.NO. : 2200014717

86,328.00

October 2016

COMPLETED

MALAYSIA MARINE AND HEAVY ENGINEERING SDN.BHD.

Nik Khaiziah

Tel No. : 07-2682111

Manpower Supply (Arc.Welder 8 pax, Fitter 8 pax, Semi skill 8 pax)

SO.NO. : 2300009814

121,264.00

October 2016

COMPLETED

MALAYSIA MARINE AND HEAVY ENGINEERING SDN.BHD.

Nujaimi Abd Aziz

Tel No. : 07-2682111

Manpower Supply for B&P Works (Helper 18 nos.)

154,800.00

Nov 2016

COMPLETED



               2015 (At July)
 

 

CLIENT ‘S NAMES

 

 

CLIENT’S CONTACT PERSON/TEL NO:

 

PROJECT NAME

 

CONTRACT VALUE

(RM)

 

PROJECT AWARDED

 

STATUS

MALAYSIAN MARINE AND HEAVY ENGINEERING SDN BHD

 

Contract Holder:

PETRONAS CARIGALI SDN BHD

 

         1) Nujaimi Abd Aziz (nujaimi.az@mmhe.com.my)

        2) Muhamad Adha Abdullah (m.adha@mmhe.com.my)

 

Tel No: 07 2682111

 

PROVISION OF MANPOWER SUPPLY – 10 NOS OF GENERAL WORKER.

 

PO/SO NO: 3900003723

90,000.00

Jul 2015

ON GOING

MALAYSIAN MARINE AND HEAVY ENGINEERING SDN BHD

Contract Holder:

SABAH SHELL PETROLUEM COMPANY

         1) Norhayati Md Rasol (norhayati.r@mmhe.com.my)

         2) En. Ajmal (ajmal@mmhe.com.my)

 

Tel No: 07 2682111

 

PROVISION OF MANPOWER SUPPLY – 2 NOS OF GENERAL WORKER.

PO/SO NO: 3900002942

13,000.00

Jan 2015

COMPLETED


ARCHITECTURAL

                2016
 
CLIENT ‘S NAMES
 
 
CLIENT’S CONTACT PERSON/TEL NO:
 
PROJECT NAME
 
CONTRACT VALUE
(RM)
 
PROJECT AWARDED
 
STATUS
PIONEER ENGINEERING (CARIGALI HESS)
 
En.Shahidan
 
Tel No: 03-2161 1100
PROVISION MANPOWER, TOOLS,EQUIPMENT,MATERIAL & CONSUMABLES SUPPLY – CKQ PLATFORM TILES REPLACEMENT
 
P.O.NO. : PO/PESB/0116/100
194,000.00 JAN 2016 COMPLETED
PIONEER ENGINEERING (CARIGALI HESS)
 
En.Shahidan
 
Tel No: 03-2161 1100
PROVISION MANPOWER, TOOLS,EQUIPMENT,MATERIAL & CONSUMABLES SUPPLY – REPAIR ROOFING
 
P.O.NO. : PO/PESB/0416/051
74,963.00 MAY 2016 COMPLETED
PIONEER ENGINEERING (CARIGALI HESS)
 
En.Shahidan
 
Tel No: 03-2161 1100
PROVISION OF DETAIL DESIGN, HYGIENE UPGRADE OF CKP KITCHEN AND FOOD STORE,SUPPLY,INSTALL & COMMISSIONING
 
P.O.NO. : PO/PESB/0416/083
90,094.70 APRIL 2016 COMPLETED
EMBER GAS TECHNOLOGY SDN BHD (OFFSHORE)
CONTRACT HOLDER : REPSOL
Fitri
Tel.No.:013-3530406
TALISMAN BOA COL WATER SYSTEM UPGRADE
 
P.O.NO.: EGT/PO/TML/ABSB/001
 
278,000.00
 
MARCH 2016 COMPLETED
MALAYSIA MARINE AND HEAVY ENGINEERING SDN.BHD.
CONTRACT HOLDER : PETRONAS CARIGALI
 
Hanif
Tel.No.: 07-268211
EPCC F12 FACILITIES PACKAGE LUMP SUM
 
S.O.NO.: 3900004960
790,000.00 APRIL 2016 ON GOING
MALAYSIA MARINE AND HEAVY ENGINEERING SDN.BHD.
CONTRACT HOLDER : MISC
 
Mohamad Hanif Bin Tumin
 
Tel No: 07-2682111
TO CARRY OUT CARPENTRY WORKS AT VARIOUS LOCATION FOR LNG PUTERI ZAMRUD
 
 
1,200,000.00 JULY 2016 ON GOING

                2014 – 2015
NO PROJECT LOCATION START FROM CONTRACT VALUE (RM) WORK DESCRIPTION
1 MALIKAI EPC TLP PROJECT MMHE MAR 2014 --
  • Architectural works
2 SK316 DEVELOPMENT PROJECT MMHE AUG 2014 --
  • Architectural works
3 BESAR-A PROJECT MMHE JAN 2015 --
  • Architectural works
4 TAPIS-B LER PROJECT KEMAMAN MAR 2015 --
  • Architectural works

               2013 – 2014
NO PROJECT LOCATION START FROM CONTRACT VALUE (RM) WORK DESCRIPTION
1 TANGGA BARAT CPP (LUMP SUM) MMHE DEC 2012 0.313 M
  • Additional Repair Works
2 ENERGY PRODUCER 6 MMHE JULY 2013 1.13 M
  • Carpentry for LQ, Refurbishment of Flooring, Ceiling, Wall ETC.
3 F14DR-A TOPSIDE & F14/F29 PROCESS MODULE MMHE AUG 2013 0.025 M
  • Supply of Pigging Trays & Work Bench
4 TAPIS A PLATFORM SHAPADU ENERGY & ENGINEERING SDN BHD JULY 2013 2.75 M
  • Supply of Specialist Teams for Upper Riser Heavy Walled Installation for Tapis A Platform
5 FABRICATION OF KBB TOPSIDES (BOAQ) MMHE AUG
2013
0.27 M
  • Manpower Supply
6 FABRICATION OF KBB TOPSIDES (BOAQ) MMHE AUG
2013
0.038 M
  • Manpower Supply
7 DAMAR-A PLATFORM (TOPSIDE) MMHE AUG 2013 0.38 M
  • Extension Manpower Supply / Piping
8 DAMR-A PLATFORM (TOPSIDE) MMHE JULY 2013 0.26 M
  • Manpower Supply / Piping
9 BOA, BRE & BRA Topside DAYANG ENTERPRISE SDN. BHD. OCT 2013 --
  • Material & manpower supply offshore for cold and hot water system change out.
10 BLOCK PM307 BERTAM FIELD DEVELOPMENT PROJECT TABUNG HAJI APR 2014 --
  • Architectural works

YEAR 2013
NO PROJECT LOCATION CONTRACT VALUE (RM) WORK DESCRIPTION
1 F14 / F29 PROCESS MODUL
(SARAWAK SHELL BERHAD)
MMHE (OBU) 0.3 M
  • Architectural Works
2 FPSO CENDOR (LABORATORY PAKAGE)
(MISC)
MMHE
(OBU)
0.9 M
  • Architectural Works
3 DAMAR A - TOPSIDE
(EXXONMOBIL)
MMHE
(OBU)
0.4 M
  • Supply and Install Door
4 F14DR-A TOPSIDE & F14/F29 PROCESS MODULE
(SARAWAK SHELL BERHAD)
 MMHE
(OBU)
1.3 M
  • Mechanical Installation Work
5 FPSO CENDOR MARINE MMHE (OBU) 0.083 M
  • Hull, Outfitting & Carpentry Works
6 MOPU CONVERSION H2504 KENCANA HL SDN BHD 0.011 M
  • Accommodation General  Cleaning Works
7 MT SCORPIUS M3NERGY OFFSHORE LTD 0.032
  • Provision of service for Asbestos Analysis
8 FMC MALAYSIA SURFACE PLANT FMC WELLHEAD EQUIPMENT SDN BHD 0.006 M
  • Supply of GV Stand
9 FPSO CENDOR MARINE MMHE 0.065 M
  • Misc. Cabin Works of 40’ Container and Temporary Office Onboards
10 WINDOW CONTAINER WILLTECH ASIA PTE LTD 0.0001 M
  • Supply and Install Container Window
11 FMC MALAYSIA SUBSEA PLANT FMC WELLHEAD EQUIPMENT SDN BHD 0.008 M
  • Supply of 8 ton Stand
12 FMC MALAYSIA SUBSEA PLANT FMC WELLHEAD EQUIPMENT SDN BHD 0.0083 M
  • Supply Mold as per Drawing Including Materials
13 FMC MALAYSIA SUBSEA PLANT FMC WELLHEAD EQUIPMENT SDN BHD 0.003 M
  • GV Stand Modification Works
14 F14DR-A TOPSIDES & F14/F29 PROCESS MODULE MMHE 0.012 M
  • Additional Louver Wall at Helideck Framing Plan
15 AMPA-9-HP COMPRESSOR MODULE KENCAHA HL SDN BHD 0.045 M
  • Supply and Install Underlayment Deckrete Latex on the LCR Roof (HP-98/99)
16 F14DR-A TOPSIDE & F14/F29 PROCESS MODULE MMHE 0.020 M
  • Additional Works Due to Various SI
17 F14DR-A TOPSIDE & F14/F29 PROCESS MODULE MMHE 0.045 M
  • Supply and Apply Choke Fast Orange Compound
18 F14DR-A TOPSIDE & F14/F29 PROCESS MODULE MMHE 0.024 M
  • Additional Works Due to Various SI
19 MMHE-ATB- PER PR 40020255 MMHE-ATB 0.0015 M
  • Supply of Hardwood

YEAR 2012
NO PROJECT LOCATION CONTRACT VALUE (RM) WORK DESCRIPTION
1
 
DHIRUBHAI DEEPWATER KG2
(TRANSOCEAN DRILLING SB)
 
WILLTECH ASIA PTE. LTD. (JOHOR PORT) 0.015 M
  • Supply Manpower & Material for Flooring Works for Drill Cabin (DOGHOUSE) Project
  • Removed rubber stud tile from Drillers Cabin A, Drillers Cabin B & Cyberbase Operator Station.
  • Removed old glue with scrapper, supplied and renewed with new rubber stud tiles.
2 KINABALU CENTRAL PROCESSING PLATFORM  (PETRONAS CARIGALI) MMHE 18 M
  • Supply, fabrication, installation, testing & pre-commissioning works
  • Architectural for Living Quarters.
  • Piping/plumbing for Living Quarters
      0.14 M
  • Variation work
3 F13K
(SARAWAK SHELL BERHAD )
KENCANA FABRICATION YARD 0.8 M
  • Architectural Works
4 E8K
(SARAWAK SHELL BERHAD)
KENCANA FABRICATION YARD 0.8 M
  • Architectural Works
5 LQ-B193 PROCESS PLATFORM
(NATURAL GAS CORP, LTD, INDIA)
HERTEL (SIME DARBY ENGINEERING SDN BHD YARD) 2.5 M
  • Installation of the complete Piping and Plumbing System
  • Architectural outfitting works
  • Supply and install (wall, floor, insulation , furniture and handrail)
6 SUNBORN BARCELONA
(SUNBORN)
BOUSTED YARD, LUMUT 0.9 M
  • MANPOWER SUPPLY
7
 
GUMUSUT-KAKAP PROJECT
(SABAH SHELL PETROLEUM CO.)
 MMHE (OBU) 15M
  • Structural Steel Works for West Module
8 WEST DESARU MOPU EPCIC
(PETROFAC E & C SDN. BHD.)
KENCANA FABRICATION YARD 0.4 M
  • Architectural Works
9 AMPA-09 HP COMPRESSION MODULE
(BRUNEI SHELL PETROLEUM)
SAPURA KENCANA PETROLEUM YARD 0.4 M
  • Architectural Works
10 MOPU H2504
(KENCANA)
SAPURA KENCANA PETROLEUM YARD 0.01 M
  • Cleaning Work
11 MT SCORPIUS (M3NERGY)
 
LABUAN SHIPYARD 0.03 M
  • Survey Asbestos

YEAR 2011
NO PROJECT LOCATION CONTRACT VALUE (RM) WORK DESCRIPTION
1
 
FPSO CENDOR PHASE II (PETROFAC) MMHE 0.12 M
  • Modification Works for upgrading FPSO Cendor PMT Office
2 MOPU (PETROFAC) KENCANA FABRICATION YARD 0.29 M
  • Architectural Works for Sepat Early Production System
3 PM318 PUTERI PIPELINE & PRODUCTION RESTORATION (NEWFIELD, PETRONAS) KENCANA FABRICATION YARD 0.35 M
  • Architectural Works

YEAR 2009-2010
NO PROJECT LOCATION CONTRACT VALUE (RM) WORK DESCRIPTION
1 WEST BELUMUT (NEWFIELD) KENCANA FABRICATION YARD 10 M
  • Architectural works
2 CPDR-A TOPSIDES (SARAWAK SHELL BERHAD) KENCANA FABRICATION YARD 0.4 M
  • Supply of manpower, materials, supervision, tools, equipment, fitting and consumables for Architectural works
3 F23R-A
(SARAWAK SHELL BERHAD)
PfcE (TELOK RAMUNIA FABRICATION YARD) 0.07 M
  • To fabricate and supply one (1) unit local make portable toilet as per client specification.
4 F23R-A TOPSIDES
(SARAWAK SHELL BERHAD)
PfcE (TELOK RAMUNIA FABRICATION YARD) 1.2 M
  • Provision of manpower, tools consumables, equipment for mechanical works
5 PLUTO LNG OFFSHORE PLATFORM TOPSIDES (WOODSIDE BURRUP PTE LTD) TELOK RAMUNIA FABRICATION YARD 0.9 M
  • Mechanical Installation Work
6 TANGGA BARAT CENTRAL PROCESSING PLATFORM – A (PETRONAS CARIGALI) MMHE 18.8 M
  • Fabrication, installation, testing & pre-commissioning works
  • Architectural for Living Quarters.
  • Piping/plumbing for Living Quarters
      0.31 M
  • Additional Repair works
7 MOPU 256
(PETROFAC)
MMHE 1.3 M
  • Architectural Work

YEAR 2008
NO PROJECT LOCATION CONTRACT VALUE (RM) WORK DESCRIPTION
1
 
NAGA – 1 ( UJD ) MMHE (SHIPREPAIR DIVISION) 0.5 M
  • Removal asbestos.
2 6 - MAN TEMPORARY LIVING QUATERS (SARAWAK SHELL BERHAD) ACTUAL BUILDER SDN. BHD - WORKSHOP 0.5 M
  • Piping works for plumbing.
  • Architectural for Living Quarters.
  • Provide electrical.
  • Provide system mini HVAC
3 ANGSI-D TOPSIDE (PETRONAS) TELOK RAMUNIA FABRICATION YARD 1.8 M
  • Piping works
  • Mechanical works

YEAR 2006-2007
NO PROJECT LOCATION CONTRACT VALUE (RM) WORK DESCRIPTION
1 KEPPEL FELS-JACK UP RIG (KEPPEL FELS) TELOK RAMUNIA FABRICATION YARD 1.5 M
  • Piping fabrication and installation work jack up rig hull side.
2 BUNGA KEKWA C ANNEX PLATFORM ( TALISMAN ) TELOK RAMUNIA FABRICATION YARD 0.7 M
  • Provision of man power, tools, consumables and supervision including installation of end closure
3 SC ( F13 E ) DR - A TOPSIDE ( SARAWAK SHELL BERHAD ) TELOK RAMUNIA FABRICATION YARD 1.9 M
  • Provision of man power, tools and supervision of piping works. Duplex piping 9000 dia inch.
4 BR - A DECK EXTENSION (TALISMAN) TELOK RAMUNIA FABRICATION YARD 0.4 M
  • Change of piping materials from galvanized carbon steel to stainless steel and supply man power for mechanical work.
5 VASAI BRIDGE (SAMSUNG) TELOK RAMUNIA FABRICATION YARD 0.8 M
  • Piping works
6 SUMANDAK SELATAN & TEPI (PETRONAS) TELOK RAMUNIA FABRICATION YARD 2.2 M
  • Piping works.
  • Architectural works for (SUJT-C & SUPG-B)
7 EAST BELUMUT – A LIVING QUARTERS (NEWFIELD) TELOK RAMUNIA FABRICATION YARD 6.4 M
  • Piping works for plumbing.
  • Architectural for Living Quarters.
YEAR 2007
NO PROJECT LOCATION CONTRACT VALUE (RM) WORK DESCRIPTION
1
 
W.D.KENT SELF TENDER BARGE (MERMAID OFFSHORE) MMHE (MARINE REPAIR) 2.0 M
  • Miscellaneous pipe renewal and conversion.
  • High pressure pipe renewal conversion.
  • Accommodation pipe renewal and conversion.
2 T.H.208 JACK UP RIG
(TANJUNG OFFSHORE)
MMHE (MARINE REPAIR) 1.1 M
  • Miscellaneous pipe renewal and conversion.
  • High pressure pipe renewal conversion.
  • Accommodation pipe renewal and conversion.
3 T – 11 SELF TENDER DRILLING BARGE (SMEDVIG) MMHE (MARINE REPAIR) 2.3 M
  • New piping work for accommodation, Brine system, fire line and other pipe system.
4 FSO ORKID (TALISMAN) MMHE (MARINE REPAIR) 2.0 M
  • Engine room renewal and conversion.
  • Accommodation pipe renewal and conversion.

YEAR 2006
NO PROJECT LOCATION CONTRACT VALUE (RM) WORK DESCRIPTION
1
 
FSO CENDOR  (MISC) MMHE (MARINE CONVERSION) 0.6 M
  • Cargo offloading pipe.
  • Miscellaneous pipe to be renewal.
2 FSO ABU CLUSTER (TALISMAN) MMHE (MARINE CONVERSION) 3.0 M
  • Accommodation piping work for sanitary and soil system. Portable water, fresh water, hot & cold water system. Modified and lay new pipe. Material CPVC galvanize pipe and conifer pipe.
  • Engine room miscellaneous, piping renewal.
  • Supply fire watch
  • Provide layout and fabrication drawing.
3 T – 10 SELF TENDER DRILLING BARGE (SMEDVIG) MMHE (MARINE CONVERSION) 2.3 M
  • New piping work for accommodation, Brine system, fire line and other pipe system.
4
 
SEW HAWK MMHE (MARINE REPAIR) 0.6 M
  • Refurbish and new installation ballast and miscellaneous pipe.
5 KDU KIKEH SPAR PROJECT (TECHNIP – MURPHY OIL) MMHE (ENGINEERING CONSTRUCTION) 1.1 M
  • Complete hull piping.


 